Manufacturing setup

Before you can write a bill of material with operations, set up the places, machines, people and processes it will refer to. Do them in this order.

StepScreenMenu
1Work CentersManufacturing → Work Center
2MachinesProduction → Machine Assets
3Labor RolesManufacturing → Labor Roles
4Production JobsManufacturing → Production Job
5Holiday CalendarManufacturing → Holiday Calendar
6Downtime ReasonsManufacturing → Downtime Reasons

Work centers​

A work center is an area of the plant with its own running cost, such as a CNC cell or the assembly line.

Work Centers

Click Add Work Center.

FieldNotes
Center Code, Center NameRequired
Machine Cost Per HourCannot be negative
Overhead %Cannot be negative
Available Hours Per DayRequired, at most 24. Used when scheduling
Department, Location, DescriptionOptional

A work center

Machines​

Machine Assets

Click Add Machine, fill in the form and click Create Machine.

FieldNotes
Machine Code, Machine NameRequired
StatusACTIVE, UNDER_MAINTENANCE, BREAKDOWN or OUT_OF_SERVICE
Work CenterRequired — the work center the machine belongs to
Cost Per HourRequired — used to cost operations run on this machine
DescriptionOptional

Adding a machine

After saving you land on the machine's own page, which shows its details, Production Logs and Status History, with buttons Edit, Log Event, Add Log and Delete.

A machine's page

Labor roles​

A labor role is a kind of worker with an hourly cost: operator, setter, welder, inspector.

Labor Roles

Click Add Labor Role: Role Code, Role Name, Cost Per Hour (all required), the Active switch and a Description.

A labor role

Production jobs​

A production job is a process in your catalogue — turning, drilling, welding, powder coating, inspection. Each operation on a bill of material points to one.

Production Jobs

Click Add Job.

FieldNotes
Job Code, Job NameRequired
ActiveSwitch off to retire a job
Default Setup Time (min)Copied into operations that use this job
Default Run Time Per Unit (min)Copied into operations that use this job
Default Piece Rate (₹ / each)For work paid by the piece
Piece UnitWhat is counted: hole, kg, test
DescriptionOptional

A piece-rate job: drilling paid per hole

:::info Piece rates If a job has a piece rate, an operation that uses it can be costed as Rate × Quantity, for example ₹2 per hole × 5 holes. Change the rate here and every operation that uses the job is re-costed. See Bill of materials. :::

Holiday calendar​

The calendar tells the scheduler which days the plant works.

Holiday Calendars

Click New Calendar: Calendar Name, Active, Description and the weekly-off days. Then open the calendar to see its month grid.

A calendar with holidays and overrides

  • + Holiday adds a company holiday: date, name and whether it is a full day.
  • + Override changes a single day: WORKING makes a holiday or weekly off a working day, OFF makes a normal working day a day off. Give the reason.

Adding a holiday

Adding a date override

Downtime reasons​

These are the reasons an operator can pick when reporting a stopped machine. Ten are provided, such as MB01 Machine Breakdown and POW01 Power Failure. Each is marked PLANNED or UNPLANNED.

Downtime Reasons

Click Add Reason to add your own: Reason Code, Description and Category.